Construction of the Chernbyl NPP

Construction of the Chernobyl nuclear power plant

Solutions

Construction of the Chernobyl nuclear power plant, on the territory of the Ukrainian Soviet Socialist Republic (USSR) (with 24.08.1991 g. independent state of Ukraine), stipulated by the construction plan (NPP construction plan for 1966-1975 years) and commissioning of nuclear power plants in the territories of the Union of Soviet Socialist Republics (the USSR) at 1966-1975 years. The construction of the Chernobyl nuclear power plant was approved by a resolution of the Council of Ministers of the USSR in 1966 year.
AT 1967 year, Council of Ministers of the Ukrainian SSR, fulfilling the above decision, identified and agreed on a land construction site, at the rate of 1676 it, near the village of Kopachi of the Chernobyl region (at 12 km from. Chernobyl), Kiev region, for the construction of the Chernobyl nuclear power plant and settlement, for accommodation for operators and builders of the Chernobyl nuclear power plant.
By order of the Ministry of Energy and Electrification of the USSR from 11 December 1969 city, established, what with 1 January 1970 g. the management of the Chernobyl nuclear power plant under construction should be organized, Viktor Petrovich Bruchanov appointed .
Since December 1971 g. to the post of head of the Construction Management of the Chernobyl nuclear power plant (Chernobyl general contractor) Vasily Trofimovich Kizima appointed.
Chernobyl construction included three phases
.
First of all included:1-2nd and 2nd power units, as separate, independent, each in its own independent building, with type reactors VVER-1000 MW. Power units put into operation: 1-th November 1977 city, 2-oh in december 1978 g.
The first phase of the Chernobyl nuclear power plant was commissioned at design capacity 2000 MW in October 1979 g.
The second phase of construction included: 3-4th and 4th power units, with reactors of the type RMBK-1000 MW, having in common housing some common components and equipment. Power units put into operation: 3-in December 1981 city, 4-passed in december 1983 g. The second phase of the Chernobyl nuclear power plant was commissioned at design capacity 2000 MW in March 1984 g.

In parallel with the construction of the Chernobyl nuclear power plant in the distance 2,5 km from the nuclear power plant was designed and built the city of Pripyat, for the residence of operators and builders of nuclear power plants.
On 26.04.1986. population of. Pripyat was 55 000 inhabitants, including about 5000 seconded builders, average age made up 26 years old.

g. Pripyat 2,5 km from the Chernobyl nuclear power plant.

 

 

 

 

 

 

 

 

On the day of the accident 04/26/1986. In the town Pripyat Was built:

377318 square meters of living space;
Kindergartens at 2420 and 2100 places;
Schools on 4052 training places;
Polyclinic of 600 visits;
Hospital on 250 beds;
12 shops;
A restaurant;
Palace of Culture "Energetik" on 800 places;
Hotel "Polesie";
Swimming pool;
The first stage of the sports complex;
Vocational School of 850 students;
Music school with a concert hall;
Cinema "Prometheus" on 420 places;
Two consumer service plants;
Dry laundry;
Sauna;
The complex of objects of the base department of the worker supply.
The third phase of the Chernobyl construction:
Включала: 5-6th and 6th power units, with RBMK-1000 MW reactors, having in common housing some common components and equipment.
Power units had a high degree of readiness on 04/26/1986.
Start 5th was scheduled in 1986., 6-in 1987. Given the prospects and design adjustments, as of 26.04.1986 city, design capacity of the Chernobyl nuclear power plant (CHAES), planned to be 9 nice- lions kilowatts and included 8 power units. Construction was planned in four phases, in each turn, two power units.
The fourth phase of the Chernobyl construction was planned with two power units: 7-8th and 8th with reactors RMBK-1500 MW each. Placement was supposed at a distance 15-20 km from the existing six Chernobyl power units.
The power units had a high degree of readiness on 04/26/1986.. Start 5th was scheduled in 1986., 6-in 1987. Given the prospects and design adjustments, as of 26.04.1986 city, design capacity of the Chernobyl nuclear power plant (CHAES), planned to be 9 nice- lions kilowatts and included 8 power units. Construction was planned in four phases, in each turn, two power units.
The fourth phase of the Chernobyl construction was planned with two power units: 7-8th and 8th with reactors RMBK-1500 MW each. Placement was supposed at a distance 15-20 km from the existing six Chernobyl power units. In parallel with the construction of the Chernobyl nuclear power plant in the distance 2,5 km from the nuclear power plant was designed and built the city of Pripyat, for the residence of operators and builders of nuclear power plants.

The organization

g. Pripyat

Supervisor

FIO

Volume per year:

Production

Electric power

or

Performed

work in rubles.

In parallel with the construction of the Chernobyl nuclear power plant since 1970.

amount

working

Chernobyl named after B. AND. Lenin

Bruchanov V.P..

28 billion kW / year

4000

Jupiter Factory

WATER CHAES (Gen. contractor)

Kizima V.T..

123 000 000 rub / year.

10000-12000

V.t.ch:

DSK — 3

Bordash V..

WHY UTEM

Tokarenko V.D..

PSU UTEM

Kozakov

WINE

Kostyrka

SMU ČES

TPO

Yuzhatomenergostroytrans

Sichkarenko

ATP – 31015

Sapiton M.N.

GRP «Gidroproekt»

Faust

YuEMV

UMSR

Olkhovsky A.A

Small mechanization

SNU GEM

READ

PRC

meeting

Levchenko

ZBI Institute

In parallel with the construction of the Chernobyl nuclear power plant since 1970

Hydraulic installation

KSMU

Luka MG.

Donbassantechmontage

Energovysotspetsstroy

Gïdrospecstroy

Neuchev VN.

МСЧ 126

Leonenko

KBO

Communication center and Soyuzpechat

Tank farm

The bitter party

City Executive Committee (apparatus)

Voloshko VP

Department of Culture

Hot

Record Store

Television

Book House

Stroybank

Bus station

Transagency

State insurance

Furniture store

Court and prosecutor's office

Indicative

SVPCH-6

Article. Janov

0

Publication author

offline 2 hours

ChAESV

0
Comments: 2public: 235Registration: 17-05-2019

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.